Government begins paying Sea Defence Contractors as coastal erosion threatens shoreline

83093

The government has started paying certified claims to contractors handling sea defence projects across the country following a validation exercise, the Minister for Works, Housing and Water Resources, Ahmed Ibrahim, has told Parliament.

Briefing lawmakers on the floor of the House, Mr Ibrahim admitted that delays in releasing funds have slowed down the pace of work on several critical coastal protection interventions. However, he assured the House that the financial bottleneck is being resolved to speed up the completion of ongoing works.

“Following the successful completion of the validation exercise on outstanding claims, government has commenced the payment of certified claims due the contractors,” he said.

">

The Minister noted that Ghana’s shoreline remains under severe threat from coastal erosion and flooding. He attributed the worsening situation to a mix of natural forces—such as storm surges, high tidal waves, and rising sea levels caused by climate change—and destructive human activities, including illegal sand winning and unregulated building along the coast.

To protect lives, property, heritage sites, and vital national infrastructure like roads and power installations, the state has stepped up its engineering interventions along the coast.

“In response to these challenges, the Ministry, in collaboration with the Ghana Hydrological Authority, has over the past decades implemented more than twenty-five coastal protection projects along various sections of the country’s coastline,” the Minister said.

Giving a breakdown of ongoing works in the Central and Western regions, Mr Ibrahim disclosed that the Cape Coast Coastal Protection Project is currently 87 per cent complete, while the Anomabu Coastal Protection Project stands at 81 per cent, with its additional works at six per cent. In the Western Region, Phase Two of the Aboadze Coastal Protection Project is 75 per cent complete, while the main Aboadze project is at 33 per cent. Additional works on the Axim Coastal Protection Project have reached 61 per cent completion, and the Dixcove project is at 36 per cent. He also noted that Phase Two of the Blekusu Coastal Protection Project is 57 per cent complete.

Once finished, these interventions are expected to shield roughly 25 kilometres of vulnerable shoreline and sustain local economic activities.

“The Ministry remains fully committed to timely completion of all ongoing sea defence projects in the Central and Western regions,” Hon. Ibrahim said.

He added that his outfit will maintain close oversight alongside the Ghana Hydrological Authority and project contractors to ensure the sea defence walls are delivered on schedule for the safety of coastal residents.

By: Rainbowradioonline.com/Ghana