The Ghana Grid Company Limited (GRIDCo) has announced the successful repair and restoration of its 330kV Aboadze–Anwomaso transmission line, returning the vital power infrastructure to full operation following disruption caused by illegal chainsaw activities.
In a press statement issued by its Corporate Communications Section on Thursday, November 26, 2026, the power transmission utility confirmed that engineering teams completed restoration works at approximately 12:07 pm, barely 24 hours after the line went down.
According to the statement, the high-voltage transmission line sustained damage on Wednesday, November 25, 2026, when illegal chainsaw operators felled a tree directly onto the overhead conductors.
“The Ghana Grid Company LTD. (GRIDCo) wishes to inform the general public that we have successfully completed repairs to the damaged 330kV Aboadze–Anwomaso transmission line, which has now been restored to operation,” the statement noted.
Technical crews were subsequently deployed to the site to clear the obstruction and carry out emergency repairs, ensuring power transmission along the corridor resumed safely by midday on Thursday.
Management of the company expressed concern over the persistent threat posed by unauthorised activities along its rights-of-way and urged citizens to join efforts in safeguarding national power assets.
“GRIDCo wishes to use this opportunity to appeal to the general public to help protect critical electricity transmission infrastructure by refraining from illegal chainsaw operations and other activities in the vicinity of transmission lines and associated facilities,” the release added.
The company further extended its gratitude to affected electricity consumers for bearing with the situation while engineers worked to resolve the fault.

By: Rainbowradioonline.com/Ghana