The Minister of Roads and Highways, Francis Asenso-Boakye, says the Adentan-Dodowa Road Project will be completed by November 2024.
The project has been characterised by delays, following which motorists and residents have complained.
The minister assured that the project would be completed by November 2024.
He said this when he paid a working visit to the site on Thursday, May 30, 2024.
He attributed the delay in the project to issues with the previous contractor and emerging developments along the corridor.
He added that the necessary process would be followed to ensure the new contractor begins work as soon as possible.
“They started seven weeks ago and already they’ve done seven kilometres, doing massive excavation works and drainage facilities and I’m very encouraged by the work that they’ve done and I’m very confident that they’ll be able to stick within the schedule and by November, the Motorist will start experiencing the benefits.”
“So we had issues with the contracts and since I’ve been here, I’ve had discussions with my officials and we are going to terminate that contract, we’ll repackage it and the project and give it to our new contractor. But I can assure you that we are going to go through the necessary process to ensure that contractors come to the site as soon as possible.”