The West African Gas Pipeline Company Limited (WAPCo) says the intermittent power outage in parts of the country recorded on Friday, March 22, was due to a system glitch at the Tema facility.
In a statement dated Saturday, March 23, 2024, WAPCo stated that its Tema facility completely shut down due to a system glitch at about 10.30 pm.
The statement said gas delivery resumed at the Tema facility for its customers in Tema at around 6.30 am Saturday.
“The West African Gas Pipeline Company Limited (WAPCo) has resumed gas delivery at its Regulating and Metering Station at Tema, Accra, after a system shut down. At about 10.30 pm last night, WAPCo’s Tema facility completely shut down due to a system glitch.
“Our engineers worked assiduously through the night, and we resumed gas delivery to our customers in Tema at around 6.30 am this morning,” Dr Isaac Adjei Doku, General Manager, Corporate Affairs said in the statement.
“WAPCo is committed to delivering safe and reliable services and is investigating the root cause of the problem to prevent a recurrence.”
Read the full statement below
By: Rainbowradioonline.com/Ghana